At the September 15, 2022 BPAC meeting, Matthew Bomberg, Alameda County Transportation Commission (Alameda CTC) Senior Transportation Engineer, will provide a presentation on the East Bay Greenway project, a regional active transportation project being planned and implemented by Alameda CTC in partnership with the City of Oakland. The project is identified in local and regional plans, including the City’s Bike Master Plan and Measure BB Transportation Expenditure Plan. Alameda CTC is currently developing conceptual plans and conducting community engagement and environmental studies for an East Bay Greenway project which can be implemented in a near-term (3-5 year) timeframe.
Project phasing
East Bay Greenway Multimodal (Phase 1)
- Provide all ages and abilities, inter-jurisdictional active transportation facility
- On-street facility, utilize parallel streets where needed
- Avoid UPRR ROW
- Deliver within 3-5 years (funding permitting)
East Bay Greenway Urban Trail (Phase 2)
- Provide all ages and abilities, inter-jurisdictional active transportation facility
- Potential linear park enhancements
- Off-street facility in UPRR/BART corridor
- Environmentally cleared in 2018
- 10+ year timeline