At the September 21, 2023 BPAC meeting, Charlie Ream and Cathy DeLuca, transportation planners from OakDOT’s Planning & Project Development team, will provide an introduction to a paving project on Telegraph Ave between 52nd Street and Woolsey Street. Staff recently kicked off the project and is seeking commissioners’ feedback on initial conceptual designs.
An excerpt of the presentation is below, followed by the full presentation.
- 52nd Ave to Woolsey St (Berkeley Border)
- Approx. 1 mile
- Oakland/Berkeley connection
- Mix of land uses
- Temescal Branch Library
- Peralta Elementary School
- Medical offices and facilities
- Restaurants, cafes, and retail
- Residential
- Paving project opportunities & constraints
- 2019 Oakland Bike Plan Let’s Bike Oakland recommends protected bike lanes on project corridor
- Project schedule
- Summer/Fall 2023 Initial Outreach
- Fall/Winter 2023 Traffic Studies & Initial Design Spring
- 2024 Outreach to Get Feedback on Initial Design (survey, community meetings)
- Late 2024 Share Final Design
- 2025 Construction Start