At the January 27, 2022 Infrastructure Committee meeting, Joe Wang, Megan Weir, Brian Sukkar, and Mandana Ashti gave an update on the Rapid Response program. The presentation [PDF] is below, followed by notes.
Activation:
A Rapid Response may be activated for traffic crashes resulting in pedestrian or bicyclist fatalities, or severe injuries to pedestrians or bicyclists who are youth or seniors. A Rapid Response may be activated for additional crashes based on the individual circumstances of a crash.
Investigation:
Engineering staff will conduct site visits and review already available data, plans, and policies to make recommendations in one or more of the following four categories:
- Maintenance Treatment
- Quick-Build Improvement
- Current Capital Project to coordinate with
- New Capital Improvement
Presentation












Presentation notes
- Proactive work responding to about 800 requests per year from the public for safety upgrades. Staff uses equity screen data to score requests and determine which receive responses.
- Also reactive opportunity to respond to safety issues at locations of fatal or high injury crash locations. This resulted in initiation of the rapid response program.
- Rapid Response program is activated via investigation after every fatal or bicyclist or pedestrian crash, fatalities or high injury crashes involving seniors or children, or other crashes as appropriate.
- Follow-up categories include:
- Maintenance
- Quick-build treatments
- Integration into current, large capital project, or
- Creation of a new, large capital project
- Example projects:
- 98th Ave and Cherry
- Paint & post crosswalk median created as rapid response, concrete median crosswalk refuge installed with flashing beacons as follow-up
- E 27th St and 23rd Ave
- Rapid response centerline posts & curbs added, and LPI walk signal phases. Shifted centerline to accommodate AC Transit buses
- Under construction now, to be completed within a week
- E 12th St and 2nd Ave
- Centerline posts & curbs added, and leading pedestrian interval (LPI) signal phases
- Existing capital project with Rapid Response collaboration: Bancroft Ave and 85th Ave
- Paving project was already scheduled for October
- Included restriping of crosswalk and buffered bike lane
- Existing capital project with Rapid Response collaboration: 10th St and Harrison
- Existing project is adding sidewalk extensions at corners.
- Rapid Response will add center island and “do not enter” signs
- Existing capital project with Rapid Response collaboration: Park Blvd and E 38th St
- Existing project will narrow and simplify intersections
- Rapid Response added temporary flexposts to reduce traffic lanes from two to one through the intersection
- New capital project from Rapid Response collaboration: Foothill Blvd and 22nd Ave
- The project was first a quick-build project added centerline posts and curbs to slow turn movements
- Longer term project was identified to upgrade traffic signals with protected left turns and leading pedestrian interval signal phases
- 98th Ave and Cherry
Discussion
- Are quick-build projects ever found to be sufficient, with no further concrete or other upgrades? Such as first installation at Harrison/23rd St.
- For paving project opportunities or other capital projects where rapid responses were installed, staff look for ways to make them more permanent.
- Some locations require less maintenance than others, paint/posts have held up.
- On what timeline is it appropriate to integrate a Rapid Response into a capital project? One year, something else?
- No defined timeline determined yet, but it’s on a case-by-case basis
- Some Rapid Response locations that were folded into other capital programs (TDA3 project at 7th/Harrison, paving project on 69th Ave) ended up being abandoned or not delivering on bike/walk safety upgrades. What happens to the Rapid Response initiative at that point?
- Those locations were managed by other staff previous to the current Rapid Response Program formation.
- Commenter suggested that current program then also look back to overlooked opportunities in preceding years, to ensure some follow-up.
- Those locations were managed by other staff previous to the current Rapid Response Program formation.
- How is the success of a rapid response installation measured? 98th/Cherry location is still seeing crashes even after the concrete island is installed.
- Separate OakDOT department is looking at safety improvements along 98th Ave more comprehensively.
- Could 98th Ave project be added as a future infrastructure committee meeting agenda request?
- Yes, it will be added to the list. Great Streets Division Manager Ami Salwan is the follow-up contact.