Coliseum Transit Village

At the December 03, 2020 Infrastructure Committee meeting, Manuel Corona gave a presentation on the Intermodal Terminal Coliseum BART/Transit Village Area Improvements.

Notes from the discussion, and the presentation are below.

Discussion

  • Glad to see Hawley getting paved, it’s been in bad condition for a long time
  • New development is coming on Hawley. Is there any opportunity to negotiate more sidewalk width? 6’ might be too narrow.
    • Will look into it, may be opportunity with other affordable housing project construction coming soon.
  • Can this project fund more bike parking/storage at Lion’s Creek?
    • Not via this project because the grantfunding is already earmarked, but will look into other opportunities

Presentation

Project background

Project limits & scope

  • 71st Ave – Snell St to Hawley St
    • Pedestrian scale lighting
    • Widen sidewalk (south)
    • Plant trees
    • Repaving
    • Update curb ramps
  • Hawley St – 71st Ave to 72nd Ave
    • Pedestrian Scale lighting
    • Repair sidewalk, curb & gutter (west)
    • Repaving
    • Update curb ramps

Project timeline

  • 12/20/2020: Execute Pass-through Agreement with BART
  • 03/30/2021: Finalize NEPA
  • 04/20/2021: Complete Final Design
  • 06/30/2021: Bid Project
  • 01/30/2022: Start Construction
  • 12/20/2022: Project Closeout

View the full presentation below or download it here [PDF].

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s