14th Avenue is a major east-west corridor that connects International Boulevard with Highland Hospital and points north of I-580. 14th Avenue is currently a relatively high-speed, 4-lane divided roadway that is a barrier for people walking between residential neighborhoods to the north and south. 14th Ave is also an important, (relatively flat) connection for people biking and is a critical gap in the network between the Foothill Blvd and MacArthur Blvd bike lanes.
The City recently completed Phase 1 of this Project, which upgraded sidewalks, pedestrian crossings, and landscaping between International Blvd. and E 19th Street.
The next phase of The 14th Avenue Streetscape project will deliver an important bicycle connection on 14th Avenue from Foothill to 27th Street/Highland Hospital. This project will form the foundation for a complete network connection north to MacArthur Blvd. This project will also make pedestrian crossing improvements and striping upgrades between E8th Street and International Blvd.
Project Schedule
Fall 2020 – Public noticing, outreach, and online survey
Summer 2021 – Complete design of roadway
Fall 2021 – Advertise project for construction
Mid-2021 – Begin construction (18 month duration)
The presentation [PDF] and notes from the presentation and discussion are below.
At the April 1st, 2021 BPAC Infrastructure Committee meeting, Cathy Chea (MTC) gave a presentation on the West Grand Avenue HOV/Bus lane extension Phase II project. The project is part of Bay Bridge Forward.
Phase 1 project opened January 2019 added 1300’ of bus/HOV-only lane
Phase 2 project proposes the following:
Bus/HOV lane westbound by converting existing shoulder from Frontage Road to Maritime Street
Multi-use 2-way path on south side of West Grand between Mandela and Maritime by extending existing sidewalk. It would be 8’ wide with a 2’ barrier.
Construction expected in 2nd half of 2021.
Notes from the presentation and discussion are below.
The 28th edition of the bi-annual Bike Oakland newsletter, “We Bike Oakland” covering Bike Plan implementation progress between July and December 2020 is now available [5.6MB PDF]. Text is copied below.
At the February 18, 2021 BPAC meeting, Catherine Payne and Audrey Harris, key members of the major projects review team, reported on current development applications under consideration (and recently approved), and shared how to participate in the application review process. The presentation is below, which highlights the four major projects in development:
98th & San Leandro PUD (planned unit development): Multiple phase project, including new streets, 399 residential units, 9 work/live units, 2,500 sf ground floor retail. Market rate (no affordable units). Status: PUD and infrastructure FDP approved, 12/20
Lake Merritt BART TOD (transit-oriented development), ENA awarded 2018: 517 du (44% affordable), 500,000 sf commercial. Status: Application review underway.
Oakland Waterfront Ballpark District (aka Howard Terminal): Up to: 35,000 seat capacity sports stadium, 3,500 seat capacity entertainment venue, 2.27 million sf commercial development, hotel facilities, 18 acres open space, 3,000 dwelling units, 8,900 parking spaces (max). Status: Draft EIR publication anticipated in Q1, 2021.
West Oakland BART TOD: 762 dwelling units (20% affordable) in 3 buildings, 440,000 sf commercial (PUD approved 2/6/19). Status: FDPs for 2 buildings (including affordable housing) and infrastructure approved November 2020.