Recommendations for ACTC COVID-19 Rapid Response Program
In late July, the Alameda County Transportation Commission (CTC) announced “the availability of $1.125 million in local Bicycle and Pedestrian Measure B sales tax funds for the deployment of a COVID-19 Rapid Response Bicycle and Pedestrian Grant Program (RRGP) to support Alameda County’s economic recovery and regrowth from the impacts of COVID-19.
The City of Oakland applied to the grant program and its application was recommended to the Alameda County Technical Advisory Committee on 29 October 2020.
Oakland’s project is for “Citywide Bicycle/Pedestrian Rapid Response Enhancements“: Enhance existing, temporary safety installations with more durable improvements, including signage, striping, markers and modular curb to build on Oakland’s Slow Streets “Essential Places” and “Rapid Response” programs.
Read MoreSan Leandro Creek Greenway Trail Project
At the October 15, 2020 BPAC meeting, Marquita Price, Director of Urban and Regional Planning for the East Oakland Collective, and David Ralston, PhD, MCP, Research fellow at the Brower Dellums Institute for Sustainable Policy and Action presented on the San Leandro Creek Greenway and community engagement for the project. The San Leandro Creek Greenway is an incoming bike and pedestrian trail being built along the surfaced San Leandro Creek running behind the neighborhoods of Columbia Gardens, Brookfield, and Sobrante Park.
Learn more about the project on the project website.
The presentation is below, as well as the 90% design plans for intersections where the greenway will cross major roadways at Hegenberger Road and 98th Avenue.
Read MoreShared Mobility Accessibility Study
At the October 15, 2020 BPAC meeting, Kerby Olsen, OakDOT Shared Mobility Coordinator, and Anh Nguyen, ADA Programs Manager, presented the findings and recommendations from the “Shared Mobility Accessibility Study”.
View the presentation below or download the full report here [46MB PDF].
Read MoreScraper Bike Halloween Ride
Saturday, Oct. 31, 2020
Meet up at 5:30pm
@85th Mini Park (1712 85th Ave. Oakland 94621)
Ride out at 7:00pm
2021-2023 BPAC Commissioner Appointment Recommendations
At the October 15, 2020 BPAC meeting, the 2021 Recruitment Committee reported back with recommendations from its review of applications of people seeking to be appointed to the BPAC. The committee is recommending Michael Lok, David Ralston, and Jeremiah Maller (alternate) be appointed for the 2021-2023 term. Commissioners are appointed by the Mayor and confirmed by City Council.
View the list of applicants and the statements from the recommended candidates below.
Read MoreOctober 2020 BPAC Agenda
Oakland Inner Harbor Pipeline Crossing – Traffic Control Plan
At the October 01, 2020 Infrastructure Committee meeting, Raffi Moughamian, Associate Civil Engineer gave a presentation on the traffic control plan for East Bay Municipal Utility District (EBMUD)’s Oakland Inner Harbor Pipeline Crossing.
- EBMUD is replacing a 1940s pipeline in the Oakland-Alameda estuary and on surrounding streets in Oakland and Alameda. The pipeline is currently seismically unsound.
- Construction cost is $28M.
- Oakland streets affected: Madison (8th to 4th Streets), Jackson (5th to 4th), 4th St (Jackson to Fallon), Fallon St (4th to end)
Notes from the presentation, discussion, and the presentation are below.
Read MoreCitywide Active Transportation Enhancement Project
At the October 01, 2020 Infrastructure Committee meeting, David Pene and Jason Cook gave a presentation on OakDOT’s Active Transportation Enhancement Project.
- Objectives
- Add physical separation to existing curbside buffered bike lanes with known issues.
- Provide safer pedestrian access to key locations.
- Implement the toolkit that was developed as part of the Curbside Class IV Bikeway Analysis and evaluate the effectiveness of these tools.
The full presentation, notes, and discussion are below.
Read MorePark Blvd Intersection Improvements
At the October 01, 2020 Infrastructure Committee meeting, Joe Wang and Brian Sukkar presented the designs for improvements at the Park Blvd/13th Ave/E 38th St and Park Blvd/Excelsior intersections.
- Project cost estimate: $2.8M
- Focuses on the Park/13th Ave/E 38th and Park/Excelsior intersections, safe routes to schools in the vicinity
View the plans and notes below.
Read More